The Paddock

Milestones

  • Community engagement

    December 2020

     

    -

     

    February 2021

    Identify priorities with residents and stakeholders to gather thoughts, ideas and aspirations for the masterplan and inform the design process.
  • Initial design ideas and proposals

    March 2021

     

    -

     

    May 2021

    The development of initial ideas to improve the The Paddock and a proposed masterplan.
  • Public consultation

    June 2021

     

    -

     

    September 2021

    Seeking detailed feedback from the community and stakeholders on the proposed masterplan and initial proposals for enhancing and protecting The Paddock.
  • Detailed design proposals

    October 2021

     

    -

     

    March 2022

    Development of detailed design proposals (RIBA Stage 3).
  • Final masterplan and technical designs

    April 2022

     

    -

     

    November 2022

    Development of a final masterplan and technical designs for implementation (RIBA Stage 4).
  • Phase 1 works (Japanese Knotweed treatment)

    January 2023

     

    -

     

    April 2023

    Comprehensive works to treat Japanese Knotweed and remediate the site.
  • Procurement of landscape contractors

    February 2024

     

    -

     

    July 2024

    Tendering for landscape contractors to deliver the Phase 2 main landscape and infrastructure works.
  • Phase 2 works (main landscape improvements)

    Summer 2024

     

    -

     

    Winter 2024

    Implementation of main works to deliver landscaping and infrastructure improvements.