Identify priorities with residents and stakeholders to gather thoughts, ideas and aspirations for the masterplan and inform the design process.
Initial design ideas and proposals
March 2021
-
May 2021
The development of initial ideas to improve the The Paddock and a proposed masterplan.
Public consultation
June 2021
-
September 2021
Seeking detailed feedback from the community and stakeholders on the proposed masterplan and initial proposals for enhancing and protecting The Paddock.
Detailed design proposals
October 2021
-
March 2022
Development of detailed design proposals (RIBA Stage 3).
Final masterplan and technical designs
April 2022
-
November 2022
Development of a final masterplan and technical designs for implementation (RIBA Stage 4).
Phase 1 works (Japanese Knotweed treatment)
January 2023
-
April 2023
Comprehensive works to treat Japanese Knotweed and remediate the site.
Procurement of landscape contractors
February 2024
-
July 2024
Tendering for landscape contractors to deliver the Phase 2 main landscape and infrastructure works.
Phase 2 works (main landscape improvements)
Summer 2024
-
Winter 2024
Implementation of main works to deliver landscaping and infrastructure improvements.